Stakeholder Communication Plan
100112 Stakeholder Communication Plan_FINAL.doc 4
2. Stakeholder Engagement
Roles and Responsibilities
2.1 The NCG project life cycle, insofar as it relates to Stakeholder Engagement has been split into
three distinguishable key stages. The first is the 'Development Framework', the second is the 'PreApplication
Consultation' and the third is the 'Planning Application'.
2.2 The roles and responsibilities for Atkins and GVA Grimley have been set out in Table 2.1 and
outline who is responsible for leading the stakeholder consultation for each of the three project
stages.
2.3 Section 4 provides a list of all stakeholders to be consulted throughout the course of the project
life cycle.
2.4 It is noted that further stakeholders/consultees who have an interest or an ability to positively
contribute to the engagement process will be identified during the initial consultation process and
that any further stakeholders identified will be the subject of review by the Project Team and, on
agreement, subsequent inclusion within this Plan.
Table 2.1 - Roles and Responsibilities of Atkins and GVA Grimley
Project Stage Description Overall Lead Support
Development
Framework
Stakeholder Communication
Plan
Atkins GVA Grimley/NCG Ltd
Contact and Liaison with ALL
Stakeholders
GVA Grimley Atkins/NCG Ltd
Meetings/Workshops/
Presentations
Atkins GVA Grimley/NCG Ltd
Stakeholder Communication
Database
Atkins GVA Grimley/NCG Ltd
Update Consultation Tracker Atkins GVA Grimley/NCG Ltd
Pre-Application
Consultation
(PAC)
Submission of Proposal of
Application Notice (PAN)
Atkins GVA Grimley/NCG Ltd
Public Consultation Events
(General Public and
Community Councils)
Atkins GVA Grimley/NCG Ltd
Meetings/Workshops with
ALL other Stakeholders
Atkins GVA Grimley/NCG Ltd
Pre-Application Consultation
Report
GVA Grimley Atkins/NCG Ltd
Update Consultation Tracker Atkins GVA Grimley/NCG Ltd
Planning
Application
Submission of Planning
Application
Atkins GVA Grimley/NCG Ltd
Liaison with ALL
Stakeholders
Atkins GVA Grimley/NCG Ltd
Update Consultation Tracker Atkins GVA Grimley/NCG Ltd
169
Appendix 11.3: NCG Stakeholder Communication Plan